Power capacity

  • 130 MW (n-1) and 100 MW (n-0)
  • 132 kV Voltage
  • Renewable energy supply

Grid

  • ~6-7 % marginal loss factor (2016–2017)
  • ~1.0 km grid line to main transformer station
  • Redundant grid point (8 power lines)

Area size

  • Today ~25 ha = 250,000 m2
  • Zoned
  • Fairly flat area including a gravel pit
  • No large settlement next to site

Time to market

  • 2021
  • Dependent on final approval from road authorities

Infrastructure

  • 30 min to Evenes international airport
  • 12 min to Nordkraft HQ / Narvik

Fiber

  • Redundant fiber access with international dark fiber
  • Several operators

Climate

  • Average yearly temperature = ~2.9 celcius (Bjerkvik)