Power capacity

  • >100 MW potential (depending on Narvik DC 1 activity)     
  • 132 kV Voltage
  • N-1 redundant (requires reconstruction => Statnett cost)

Grid

  • ~7% marginal rate loss percentage (2016 – 2017)
  • ~ 0 km grid line to transformer station
  • Redundant grid point

Area

  • Today ~6 ha = 60,000 m2
  • Zoning started
  • Fairly flat area
  • No large settlement next to site

Fiber

  • Fiber access 
  • Several operators (Kysttele, Telenor, Stamfiber, Statnett)

Time to market

  • 2020. Dependent on transformer solution and final approval from Statnett/NVE

Infrastructure

  • 45 min to Evenes international airport
  • 20 min to Nordkraft HQ / Narvik

Climate

  • Average yearly temperature = ~2.9 celcius (Bjerkvik)