Power capacity

  • 200 MW reserved
  • 420/132 kV Voltage, 2 transformers today (550 MVA) 
  • N-1 redundant

Grid

  • ~6-7 % marginal loss factor (2016–2017)
  • ~250 m grid line to main transformer station
  • Redundant grid point

Area

  • ~61 ha = 610,000 m2
  • Zoning for data center/industry purposes in progress
  • Mainly flat agricultural land
  • No large settlement next to site

Time to market

  • 2022. Dependent on transformer solution and final approval from Statnett/NVE 

Infrastructure

  • 50 min to Bardufoss airport (primary)
  • 2 hours 5 min to Nordkraft HQ / Narvik

Fiber

  • Redundant fiber access with international dark fiber
  • Several operators (BBFT, Broadnet, Telenor and Statnett)

Climate

  • Average yearly temperature = ~2.0 celcius (Storsteinnes)