Power capacity

  • 200 MW 
  • 420/132 kV Voltage, 2 transformers today (550 MVA) 
  • N-1 redundant

Grid

  • ~6-7 % marginal rate loss percentage (2016–2017)
  • ~1.3 km grid line to main transformer station
  • Redundant grid point

Area

  • ~9.5 ha = 95,000 m2
  • Expansion potential
  • Zoning started for industry purposes
  • Fairly flat forest area
  • No large settlement next to site

Fiber

  • Fiber access 
  • Several operators (BBFT, Broadnet, Telenor and Statnett)

Time to market

  • 2020. Dependent on transformer solution and final approval from Statnett/NVE 

Infrastructure

  • 50 min to Bardufoss airport (primary)
  • 2 hours 5 min to Nordkraft HQ / Narvik

Climate

  • Average yearly temperature = ~2.0 celcius (Storsteinnes)