Power capacity

  • 150 MW potential (depending on Narvik DC Kvanndal activity) 
  • 420/132 kV Voltage
  • N-1 redundant (requires reconstruction => Statnett cost)

Grid

  • ~7% marginal loss factor (2016 – 2017)
  • ~ 0 km grid line to transformer station
  • Redundant grid point

Area

  • Today 88 ha = 880,000 m2
  • Zoning in progress
  • Fairly flat area
  • No large settlement next to site

Time to market

  • 2026. Dependent on transformer solution and final approval from Statnett/NVE

Infrastructure

  • 45 min to Evenes international airport
  • 15 min to Nordkraft HQ / Narvik

Fiber

  • Redundant fiber access with international dark fiber
  • Several operators (Kysttele, Telenor, Stamfiber, Statnett)

Climate

  • Average yearly temperature = ~2.9 celcius (Bjerkvik)